Figure 16. The image on the right illustrates about 75% of the MEP objects to be place into the Building B. The image on the right illustrates the partial curtain wall enclosure and slabs.
The design for this building B calls for a 2 foot raised floor system, a very new way of creating a plenum sub floor. All the ducts, electrical, network cables were placed on the concrete floor.
|